§ Matthew TaylorTo ask the Secretary of State for Transport, Local Government and the Regions (1) at which discount rate used for the sensitivity analyses of the effect of changing discount rates on the relative levels of the public sector comparator and the bids for the London Underground PPPs a switching point or switching points were found; and if he will make a statement; [10464]
Incidents, which were a cause of significant train delays and cancellations on Tuesday, 23 October 2001 Time Location Nature of incident Delay (minutes) 04.24 Royal Oak Late engineering work. Hammersmith & City Line suspended between Edgware Road to Hammersmith. Circle Line stock was prevented from reaching the service area from Hammersmith depot. 59 04.59 Rayners Lane No signalman. Service suspended on the Piccadilly Line between South Harrow to Uxbridge and Metropolitan Line between Harrow-on-the-Hill and Uxbridge. 66 05.18 Blackfriars Late engineering work. District Line suspended between South Kensington and Whitechapel. 28 06.08 Watford Alleged (subsequently unfounded) signal irregularity. Metropolitan Line suspended between Northwood and Watford. 85 08.06 Canary Wharf Jubilee Line suspended between Canary Wharf and Stratford due to security alert (white powder found). 65 09.01 Whitechapel Security alert. Suspensions on the District (Tower Hill to Whitechapel), Hammersmith & City (Plaistow to Liverpool Street) and East London Lines (Shoreditch to Canada Water), due to a suspected World War II bomb (found to be a pipe). 75 10.45 Mansion House Fire alert. Westbound service on the Circle and District Lines delayed. 20 11.23 Gloucester Road Fire alert. Westbound service on the Circle and District and Lines delayed. 25 11.48 High Street Kensington Fire alert. Service suspended between High Street Kensington and Edgware Road on the Circle and District Lines. 47 15.24 High Street Kensington Report of persons on track. District Line suspended between Earls Court and Edgware Road. Circle Line suspended. 68 16.50 Stratford Signal failure. Eastbound service on Jubilee Line delayed. 16 17.23 Moorgate Signal failure. Metropolitan, Circle and Hammersmith & City Lines suspended between Edgware Road and Aldgate. 45 18.09 North Greenwich Signal failure. Jubilee Line suspended between London Bridge and Stratford. 203 18.19 Ealing Broadway Security alert. Services suspended to North Acton (Central Line) and Turnham Green (District Line). 34 22.19 London Bridge Security alert. Northern Line suspended between Kennington to Camden Town. 22 23.31 Royal Oak Obstruction on track. Hammersmith & City Line suspended between Edgware Road and Hammersmith. 45
§ Ms Bridget PrenticeTo ask the Secretary of State for Transport, Local Government and the Regions what plans his Department has to replace the current fixed block signalling system on London Underground lines with
10W(2) which discount rates were used for sensitivity analysis of the effect of changing discount rates on the relative levels of the public sector comparator and the bids for the London Underground PPPs; and if he will make a statement. [10472]
§ Mr. JamiesonThe Government's plans for a publicly run, privately built tube will deliver around £l 3 billion of investment to improve the underground's infrastructure over the next 15 years. London Transport has yet to receive final bids on these plans. Consequently, it is too early to say whether changing the discount rate will lead to a switching point.
When final bids are received they will be evaluated for value for money on a variety of financing and discounting scenarios.
§ Ms Bridget PrenticeTo ask the Secretary of State for Transport, Local Government and the Regions how many lines on the London Underground were subject to delayed or cancelled services on Tuesday 23 October; what the cause and length of the subsequent delay was for each line; and if more than one line was affected at any one time. [11559]
§ Mr. JamiesonThis is an operational matter for London Underground, which confirms that 10 lines (Central, Circle, District, East London, Hammersmith & City, Jubilee, Metropolitan, Northern, Piccadilly, Waterloo & City) were affected by delays (of at least 15 minutes) and/or cancellations. They have provided details of delays, their cause and duration as follows:
more modern systems; if the moving block computerised system has been considered as an alternative; and when new systems are likely to be implemented. [11561]
11W
§ Mr. JamiesonThis is a matter for London Underground Ltd. to consider.
London Underground has undertaken £84 million of signalling improvements since the Government announced plans for the modernisation of the tube on 20 May 1998. A further £27 million of improvements are being undertaken in this financial year.
The tube modernisation plans will deliver a massive increase in the level of investment across the underground. Examples of signalling improvements to be delivered in the first period of the contracts include new signals on the Northern line to get the full benefit from the new trains; replacement of the Victoria line signals as part of a complete modernisation package; an upgrade of the Jubilee line signalling; a new signalling control centre on the Piccadilly line; improved signal reliability on the Bakerloo line; and greater signal capacity for the Waterloo and City line. In addition, all the signalling on the Circle, District and Metropolitan lines will be renewed in the next 10 years.
The signalling improvements to be delivered are specified in terms of the outputs required; it is for bidders to decide what type of technology will best achieve the necessary results.
§ Ms Bridget PrenticeTo ask the Secretary of State for Transport, Local Government and the Regions how many delays on London Underground were reported to have been caused by problems with(a) track and signalling and (b) rolling stock in the latest year that figures are available; and if he will make a statement. [11560]
§ Mr. JamiesonThis is an operational matter for London Underground, which defines delays as intervals of 15 minutes or more, which is the threshold for granting refunds to passengers under the customer charter. In 2000–01, the latest complete year for which data on delays are available, delays were attributed as follows:(a) track on 236 occasions, and signals on 662 occasions; (b) rolling stock on 569 occasions.