HC Deb 05 November 2001 vol 374 c26W
Mr. Hancock

To ask the Secretary of State for Defence how much time HMS Ocean spent in dock undergoing repairs, before being handed over to the Royal Navy; how much time she has spent in service at sea, since she was handed over to the Royal Navy; and if he will make a statement. [11755]

Mr. Ingram

During the period between HMS Ocean's launch in October 1995 and her handover to the Royal Navy in March 1999, she spent some 15 weeks in dock undergoing repairs. Since then, she has been available for programming, either at sea or in harbour, for a total of 904 days.