HC Deb 19 December 2001 vol 377 c512W
Mr. Bercow

To ask the Secretary of State for Transport, Local Government and the Regions (1) how many people are employed in the construction of the Aston Clinton Bypass; [22558]

(2) what his most recent estimate is of the cost of construction of the Aston Clinton Bypass in the Buckingham constituency. [22566]

Mr. Jamieson

I have asked the Chief Executive of the Highways Agency, Tim Matthews, to write to the hon. Member.

Letter from Tim Matthews to Mr. John Bercow, dated 19 December 2001: I have been asked by the Transport Minister, David Jamieson, to reply to your recent Parliamentary Questions about the Aston Clinton bypass. The contract price for the by-pass was £21.7 million. I am afraid it is not possible to disaggregate a value for the part of the by-pass that is in the Buckingham constituency. During November, 51 people were employed on the contract but numbers fluctuate from month to month depending on the nature of the work. If you would like any further information please, contact Andy Finch the Project Sponsor in our Dorking office, who will be pleased to help you. He can be contacted on 01306–878343.