HC Deb 02 March 2000 vol 345 c331W
Mr. Cohen

To ask the Secretary of State for the Environment, Transport and the Regions, pursuant to his answer to the hon. Member for Carshalton and Wallington

Indicative projection of 15 Year investment expenditure
£million 1999–2000 prices
Stations Lifts and escalators Trains Track Civil infrastructure Communications Management systems Signalling Total
Bakerloo 100 50 90 60 40 10 20 20 390
Central, Waterloo and City 220 90 100 160 100 30 10 70 780
Victoria 220 30 250 90 40 10 10 250 900
Northern1 320 70 180 40 10 20 310 950
Jubilee2 80 50 40 60 20 20 10 280
Piccadilly 220 50 500 180 50 20 20 150 1,190
Metropolitan, Circle, Hammersmith and city 330 20 590 210 170 40 10 330 1,700
District 210 20 250 130 100 30 10 220 970
East London3 50 10 130 10 200
1 Northern Line train investment costs are contracted for under a separate PFI scheme and are excluded from these figures.
2 Excludes operating and maintenance costs for the Jubilee Line Extension project.
3 Excludes costs from potential project for extending East London Line.