HC Deb 05 March 1999 vol 326 c926W
Mr. Duncan Smith

To ask the Secretary of State for Social Security what the total expenditure on the NIRS2 computer system has been to date; what the estimated total expenditure on completion of the NIRS2 computer system is; and what the original bid by Andersen Consulting for setting up the NIRS2 computer system was. [75182]

Mr. Timms

Payments for the NIRS2 service commenced from 13 July 1998. Expenditure to date has been £2.85 million. Andersen Consulting (AC) are contracted to provide the NIRS2 service until 5 April 2004. Due to the delayed go-live of the NIRS2 system, it is currently estimated that £39 million will be paid to AC for NIRS2 in that time. The bid submitted by AC for designing, developing, implementing and maintaining the NIRS2 service to 5 April 2004 was £44.8 million.