HC Deb 11 January 1999 vol 323 cc34-5W
Mr. Cousins

To ask the Secretary of State for the Environment, Transport and the Regions what(a) highway improvement and (b) major highway maintenance have been carried out along the A1 corridor from the Eighton Banks interchange north to the Scottish Border in the last three years; indicating the length in mileage and duration of the works involved. [64681]

Ms Glenda Jackson

I have asked the Chief Executive of the Highways Agency, Mr. Lawrie Haynes, to write to my hon. Friend.

Letter from Lawrie Haynes to Mr. Jim Cousins, dated 11 January 1999: The Secretary of State for the Environment, Transport and the Regions has asked me to reply to your recent Parliamentary Question. You asked "What highway improvement and major highway maintenance has been carried out along the A1 corridor from Eighton Banks interchange to the Scottish Border in the last three years". The tables attached set out the information you require. The durations shown are the duration of the works, and do not reflect the extent of any lane closures, etc on the Al. For example, the Lobley Hill to River Derwent scheme was completed using night time only closures resulting in little or no delays to traffic throughout the 3 month contract period. I trust the above information meets your requirement.

Highways Maintenance schemes carried out on the Al between Eighton Banks and the Scottish Border (over £50k) November 1995—November 1998
Scheme Length in miles Duration
A1 Scremeston Roundabout 0.25 2 weeks
A1 Smearfield 0.75 2 weeks
A1 Kingsway to Lobley Hill 1.5 2 months
Al Lobley Hill to Blaydon Bridge 0.2 1 week
A1 South of Alnwick 0.8 2 weeks
Al Fenwick Stead to Granary 0.5 2 weeks

Highway improvements carried out on the AI between Eighton Banks and the Scottish Border (over £50k) November 1995—November 1998
Scheme Length in miles Duration
A1 Seven Mile House to Stannington Bridge (Marginal Strips/Maintenance) 2.1 miles 3 months
A1 Hitchcroft to Cawledge (Additional C/Way) 1.7 miles 6 months
A1 Hitchcroft to Cawledge Southbound carriageway (Marginal Strips/Maintenance) 1.4 miles 1 month
A1 Lobley Hill Junction (Partial Signal Control) Not applicable 2 weeks
A1 Loughend Farm (Diverge Taper) Not applicable 3 weeks
A1/C137 Burgham Farm Junction (Junction improvement) Not applicable 1 month
A1/B1342 Belford Junction (Diverge Taper) Not applicable 1 month

Other Minor Schemes
Signing/Roadmarking 11
Red surfacing at junctions 20
Safety Fencing 8
Anti-skid treatment 2
Speed Cameras 5
Cycle Crossings 3
Central Reservation Hardening 2