HC Deb 21 December 1999 vol 341 c468W
Mrs. Gilroy

To ask the Secretary of State for Defence if he will make a statement on the progress of the BOWMAN project. [104129]

Mr. Kilfoyle

We have been reviewing the BOWMAN Tactical Communications System project. In accordance with Smart Procurement principles, it is now planned to deliver the system incrementally. As a consequence, initial deliveries of the stand-alone, Personal Role Radio element of BOWMAN should now be possible earlier than previously planned.

The MOD's preferred supplier for BOWMAN is Archer Communications Systems Ltd. (ACSL). Management of ACSL is now vested in BAe Systems who have committed to a radical reinvigoration of the company. ACSL is working under a risk of reduction contract to deliver a viable solution to the BOWMAN requirement. The company's original proposal was too expensive and carried too much risk. Since June, we have, therefore, been working with ACSL to produce an acceptable solution. This will depend in part on efficiencies being achieved by the company.

We now hope to place an implementation contract in late 2000. We cannot yet set a revised in service date, but would expect it to be in late 2003/early 2004.