§ Mr. TrendTo ask the Chairman of the Accommodation and Works Committee what was the nature of the work carried out on the Lower Ground Floor Secretaries' Room which necessitated the removal of personnel and equipment to temporary accommodation from 4 August to 1 September; on what date the work commenced; and for how many days the room was required to be unoccupied. [55391]
§ Sir Sydney ChapmanAn Automatic Fire Detection system was installed in the Lower Ground Floor Secretaries' area. The decanting process commenced on the 4 August with re-occupation on 1 September. The conditions of the contract give the contractor possession of the site from 4 August for 27 days and work started on 8 August.