§ Mr. BrakeTo ask the Secretary of State for the Environment, Transport and the Regions, pursuant to his answer of 5 March 1998,Official Report, column 696, during which period is the wider set of cross-system and cross-site year 2000 validation tests for the NATS systems expected to take place. [49864]
§ Dr. StrangCross-system and cross-site year 2000 validation testing on NATS systems is due to take place in the period September to December 1998.
§ Mr. BrakeTo ask the Secretary of State for the Environment, Transport and the Regions, pursuant to his answer of 5 March 1998,Official Report, column 696, if he will make a statement on the progress of the independent audit of the NATS year 2000 activities. [49865]
116W
§ Dr. StrangThe initial stage of the independent audit has been conducted and a report was produced in early May. Agreed recommendations are now being implemented. Further audit stages are due to be conducted at approximately 3 month intervals.
§ Mr. BrakeTo ask the Secretary of State for the Environment, Transport and the Regions, pursuant to his answer of 5 March 1998,Official Report, column 696, how many of the 99 NATS software items found to be Year 2000 non-compliant have been fixed; and what is the expected completion date for the fixing and testing of these changes. [49863]
§ Dr. StrangBy the end of July 1998, remedial work on 79 of the 99 non-compliant operational systems and equipment will have been completed. The plan remains to have all non-compliant items fixed and tested by the end of December 1998.