HC Deb 06 April 1998 vol 310 cc78-9W
Mr. Gummer

To ask the Minister without Portfolio for what reasons the original contractor for the Millennium Dome covering was not invited to supply the preferred environmentally friendly covering. [37690]

Mr. Mandelson

Koch Hightex submitted tenders to the New Millennium Experience Company (NMEC) for both PVC and PTFE roof covering. The NMEC concluded, however, that the bid from Birdair for the supply of PTFE represented better value for money.

Mr. Gummer

To ask the Minister without Portfolio what arrangements for compensation for the original contractor for the covering of the Millennium Dome have been made; and what sum is involved. [37691]

Mr. Mandelson

Provisions for compensation in the event of termination were contained in the contract between Koch Hightex and the New Millennium Experience Company (NMEC). Negotiations are underway between Koch Hightex and the NMEC as to the amount.