HC Deb 30 July 1997 vol 299 cc389-91W
Mr. Jack

To ask the Secretary of State for Health if he will make a statement on the timetable of project targets for each of the major hospital PFI schemes selected to continue towards financial close under the first prioritisation exercise announced on 3 July. [11039]

Mr. Milburn

The selected private finance initiative schemes will have the objective of reaching an early and acceptable financial close over the next 18 months. Officials are now preparing programmes and milestones for these schemes.

Mr. Jack

To ask the Secretary of State for Health which companies or consortiums are involved in each of the major hospital PFI schemes selected under his Department's first prioritisation exercise announced on 3 July. [11038]

Mr. Milburn

The consortiums and the constituent companies for the 14 major acute sector hospital PH schemes selected to continue towards financial close under the first prioritisation exercise are as follows:

Mr. Jack

To ask the Secretary of State for Health if he will list the time table for construction for the Dartford and Gravesham and the Norfolk and Norwich PH hospital projects. [11040]

Mr. Milburn

The Norfolk and Norwich Healthcare national health service trust and Dartford and Gravesham NHS trust are working with their private sector partners to the following timetables for the construction of new hospitals under the private finance initiative:

Start on site Completion
Norfolk and Norwich Healthcare NHS Trust Spring 1998 Spring 2001
Dartford and Gravesham NHS Trust August 1997 Autumn 2000