HC Deb 03 February 1997 vol 289 c484W
Mr. Gordon Prentice

To ask the Secretary of State for Defence, pursuant to his answers of 23 January,Official Report, column 686, if he will list the (a) uncommitted and (b) unspent parts of the sum allocated to the Trident programme. [13646]

Mr. Arbuthnot

A breakdown of the remaining expenditure on the Trident procurement programme is as follows:

£ million
Uncommitted Unspent commitment
Submarine 136 260
Strategic weapon system 303 154
Tactical weapon system 0 62
Buildings/works 7 1
Dockyards 256 2
Warhead/miscellaneous-unallocated contingency 161 71
Totals 863 550

Forward to