HC Deb 28 November 1996 vol 286 c361W
Mr. Battle

To ask the President of the Board of Trade how many applications his Department has received for combined-cycle gas turbine power stations since 1990; and how many are awaiting decision. [6296]

Mr. Page

Forty-three applications for new combined-cycle gas turbine power stations have been received to date. Three of these were received before 1990. Eleven are awaiting decision and five have been withdrawn.

Mr. Battle

To ask the President of the Board of Trade how many combined-cycle gas turbine power stations are currently under construction; and what is the total coal burn equivalent of these stations. [6298]

Mr. Page

The only available data to hand are from the National Grid Company's seven-year statement. This indicates that 2 GW of CCGT capacity, with connection agreements in place, is under construction. The effect of new CCGT generating capacity on other plant will depend on the operating regime adopted at the time.

Mr. Battle

To ask the President of the Board of Trade how many section 36 of the 1989 Electricity Act applications for combined-cycle gas turbine power stations have been granted to date. [6297]

Mr. Page

Twenty-seven applications for new combined-cycle gas turbines power stations have been granted to date.