§ Ms ChurchTo ask the Chancellor of the Exchequer how many information technology projects have been undertaken since 1992 and are planned for the coming year, in cost bands of £1,000,000. [1898]
§ Mrs. Angela Knight[holding answer 7 November 1996]: The total number of information technology projects undertaken by the Treasury, within the costs bands and years stated, are shown in the table:
There were no IT projects with a value greater than £4 million from 1992 to 1996 and there are none planned for 1997–98.
Projects undertaken in year Project value 1992–93 1993–94 1994–95 1995–96 1996–97 1997–981 £10,000-£1 million 13 17 12 23 25 7 £1 million-£2 million 0 0 1 0 0 0 £2 million-£3 million 0 0 0 1 0 0 £3 million-£4 million 0 0 0 1 0 0 1 Planned.