HC Deb 05 June 1996 vol 278 c488W
Mr. Murphy

To ask the Secretary of State for Wales what is the name of the contractor currently working on the Pontypool bypass; and if financial penalty clauses were included in the contract. [30808]

Mr. Gwilym Jones

Shepherd Hill Civil Engineers Ltd. is the contractor for the A4042 Cwmbran roundabout improvement.

The contract allows for liquidated damages to be applied in the normal way for late completion.

Mr. Murphy

To ask the Secretary of State for Wales when roadworks on the Pontypool bypass, A4042, will be completed. [30979]

Mr. Jones

The roadworks on the A4042 Cwmbran roundabout are currently scheduled to finish on 15 June 1996.