HC Deb 18 July 1996 vol 281 cc646-7W
Dr. David Clark

To ask the Secretary of State for Defence how many units of service married quarters accommodation are currently under construction; and at what cost to his Department. [37738]

Mr. Soames

[holding answer 16 July 1996]: Some 53 officers' married quarters are currently being demolished and rebuilt at an estimated cost of £4.5 million.

Dr. Clark

To ask the Secretary of State for Defence if he will make a statement on the cost of constructing new married quarters at Catterick garrison. [37737]

Mr. Soames

[holding answer 16 July 1996]: The provision of 86 quarters at Belton park, Catterick, at the end of last year cost £4.7 million. Further plans to demolish and rebuild 529 quarters at Pleasantdale, Leadmill and Waitwith/Warell estates will cost in the region of £33 million.