HC Deb 16 July 1996 vol 281 c437W
Miss Lestor

To ask the Secretary of State for Transport what is the target time scale for dealing with applications under the Transport and Works Act 1992 following receipt of the inspector's report; and what current delays there are in processing such applications. [37003]

Mr. Norris

In cases where a public inquiry is held, the target time scale is to issue the decision letter not later than six months from the receipt of the inspector's report. This time scale may be exceeded because of pressure of other work, though the staffing of the processing unit is kept under review with the target in mind, or because of the difficulty or complexity of a particular case.