HC Deb 10 July 1996 vol 281 c184W
Mr. Gordon Prentice

To ask the Secretary of State for Defence, pursuant to his answer of 2 July,Official Report, column 387, if he will give a breakdown of the £700 million yet to be spent on the Trident programme. [36231]

Mr. Arbuthnot

The £700 million of committed expenditure which has yet to be spent forms part of an estimated £1.61 billion of remaining expenditure on the Trident acquisition programme. A breakdown of the estimated remaining expenditure figure is:

£ million
Submarine 487
Strategic weapon system 516
Tactical weapon system 70
Buildings/works 11
Dockyards 266
Warhead/miscellaneous—unallocated contingency 260