§ Mr. MorganTo ask the Secretary of State for Transport what level of delay in the completion of the M5 link road with the second Severn crossing will trigger penalty clauses against the contractors. [35676]
§ Mr. WattsAny delay in substantial completion of the M49, which links the M5 to the second Severn crossing, beyond the contract completion date would render the contractor liable for a sum based on liquidated damages.