§ Ms LynneTo ask the Secretary of State for Social Security what has been the amount of down time recorded for the Child Support Agency's operational accounting system in each months since April 1993. [4077]
§ Mr. Andrew MitchellThe information is not available in the format requested. The available information is in the table.
Period Service availability percentage 3 August 1994–9 August 1994 99.8 15 August 1994–21 August 1994 97.6 28 August 1994–4 September 1994 99.6 5 September 1994–11 September 1994 99.6 12 September 1994–18 September 1994 99.9 19 September 1994–25 September 1994 99.6 14 November 1994–20 November 1994 99.6 28 November 1994–4 December 1994 99.6 9 January 1995–15 January 1995 99.2 6 March 1995–12 March 1995 99.7 27 March 1995–2 April 1995 99.8 12 June 1995–18 June 1995 99.7 26 June 1995–2 July 1995 98.9 31 July 1995–6 August 1995 99.6 7 August 1995–13 August 1995 99.7 14 August 1995–20 August 1995 99.8 6 November 1995–12 November 1995 99.7 The operation accounting system went live on 7 June 1994.