§ Mr. KeyTo ask the Secretary of State for Transport if he will list the trunk road improvement schemes which he has reassessed following the recommendations of the Standing Advisory Committee on Trunk Road Assessment and indicate for each such scheme the impact on traffic induction forecasts and on economic appraisals. [3968]
805W
§ Mr. Watts[holding answer 25 November 1996]I have asked the chief executive of the Highways Agency to write to my hon Friend.
Letter from Lawrie Haynes to Mr. Robert Key, dated 6 December 1996:
The Secretary of State for Transport has asked me to reply to your recent question asking if he will list the trunk road improvement schemes which he has reassessed following the recommendations of the Standing Advisory Committee on Trunk Road Assessment, and indicate for each such scheme the impact on traffic induction forecasts and on economic appraisals.We are carrying out SACTRA assessments for all schemes in the National Trunk Roads Programme. So far, 63 schemes from the 1996 Trunk Roads Programme have been assessed.The schedule classifies schemes into simple, intermediate and complex categories. Simple schemes are those where induced traffic effects are not considered to be significant and no further traffic or economic assessment is required. They are listed at Annex A. Intermediate schemes generally require a more flexible test to assess induced traffic and economic effects. Complex schemes are assessed in the same way as intermediate schemes but also require further detailed analysis.The further assessments for intermediate and complex schemes are being undertaken as part of general scheme preparation. Results are being produced for key stages such as public consultation and publication of draft Orders. Completion of all the assessments will, therefore, take some time. The table at Annex B shows the results for those schemes which have had detailed assessments completed. Annexes C and D are lists of the schemes in the intermediate and complex categories respectively for which the further assessments have yet to be carried out.The assessments indicate that the volume of additional traffic induced by schemes is generally less than 10 per cent., and in many cases below 5 per cent. Nevertheless, there can be significant variations on this; for example where substantial new development follows a road opening.The economic assessment process for induced traffic is still being developed and improved. For now, where induced traffic is likely to be a significant factor, we are undertaking sensitivity tests based on assumptions that provide an extreme test of scheme economics. For example, in some cases sensitivity has been tested with significantly higher volumes of induced traffic than are expected. I am pleased to say that, so far, although there are some significant reductions in Benefit Cost Ratio, none of the schemes assessed have failed the tests, even where unrealistically high levels of induced traffic have been assumed, and all have remained good value for money.Annex A: National trunk road schemes—preliminary SACTRA classificationsSimple
- A2 Lydden—Dover Improvement
- A205 Catford Town Centre Improvement
- A303 Winterbourne Stoke Bypass
- A303 Ilminister Bypass Improvement
- A303 Sparkford—Ilchester improvement
- A30/A303 Marsh Honiton and A35 Honiton Eastern Bypass
- A35 Tolpuddle—Puddletown Bypass
- A417 North of Stratton—Nettleton Improvement
- A419 Latton Bypass
- A419/A417 Cirencester and Stratton Bypass
- A428 Norse Link Road
- A43 Geddington Bypass
- A564 Doverridge Bypass
- A595 Parton—Lillyhall Improvement
- A6 Rothwell—Desborough Bypass
- A65 Hellifield and Long Preston Bypass
- A65 Manor Park Bends Improvement
806 - A69 Haltwistle Bypass
- M23 Jns 8–9 Widening
Note:
The classifications shown above are preliminary and may change as a result of further detailed analysis.
Annex B: National trunk road schemes—preliminary induced traffic appraisal Scheme Reduction in benefit to cost ratio Per cent. Amount of induced traffic Per cent. A13 Ironbridge-Canning Town Improvement 37 5 Al3 Movers Lane Junction Improvement 23 5 A13/A112 Prince Regent Lane Junction Improvement 38 5 A13/A117 Junction Improvement 38 5 A 19 Norton-Parkway Interchange Improvement 2 5 Al(M) Alconbury-Peterborough 21 5 A249 Iwade Bypass-Queenborough Improvement no change 125 A27 Worthing-Lancing Improvement (now withdrawn) 30 5 A30 Honiton to Exeter Improvement 30 10 A34 Newbury Bypass 17 10 A36 Salisbury Bypass 15 5 A453 Clifton Lane Improvement 21 5 A556(M) M6-M56 Link Improvement no change 5 A6(M) Stockport North/South Bypass [...]5 5 M40 Jn 1A-3 Widening 41 5 The reduction in Benefits to Cost Ratio (BCR) compares the induced traffic appraisal with the original fixed trip matrix evaluation.
The amount of induced traffic is an approximate figure based on the number of additional trips induced by the scheme compared with the do-minimum trip matrix.
1Indicates induced traffic includes major new development dependent on the scheme.
Annex C: National trunk road schemes—preliminary SACTRA classifications
- Intermediate
- Al20 Stansted-Braintree Improvement (S272)
- A1(M) Ferrybridge-Hook Moor Improvement
- A21 Lamberhurst Bypass
- A259 Bexhill and Hastings Western Bypass
- A2/A282 Dartford Improvement
- A3 Hindhead Improvement
- A34 Chieveley/M4 Jn 13 Improvement
- A40 Western Circus Junction Improvement
- A43 Moulton-Broughton Improvement
- A43 Silverstone Bypass
- A43 Whitefield Turn-Brackley Hatch Improvement
- A564 Derby Southern Bypass Contract A
- A6 Clapham Bypass
- A6 Great Glenn Bypass
- A6 Rushden and Higham Ferrers Bypass
- A63 Castle Street Hull Improvement
- MI-A1 Link Road Lofthouse-Bramham
807 - M1 jns 25–28 Widening
- M11 jn 5 North Facing Slip Roads
- M2 jns 1–4 Widening
- M25 Terminal 5 Spur (Heathrow)
- M4 jns 8(9)–10 Widening
- M6 Jns 11A–16 Widening
- M6 Jns 16–19 Widening
- M63 Jns 6–9 Widening
Note:
The classifications shown above are preliminary and may change as a result of further detailed analysis.Annex D: National trunk road schemes—preliminary SACTRA classifications
Complex
- Al Gateshead Western Bypass
- M1 Jns 10–14 Widening
- M1 jns 6A–10 Widening
- M25 jn 12–15 Widening
- M25 jn 15–16 Widening