HC Deb 25 October 1995 vol 264 c726W
Mr. Redmond

To ask the Secretary of State for the Environment if the nuclear installations inspectorate in respect of the magnox reactors at Wylfa power station consider whether a grab dropped into a fuel channel was specifically considered in the hazard and operability study; what their assessment of the minimum resistance to gas-flow passed by such an obstacle as a grab was; if they have discovered how many components needed to fail before the grab dropped off; what required modifications have been carried out to prevent a recurrence; when they were implemented; and if he will make a statement. [39069]

Sir Paul Beresford

The circumstances surrounding the failure of the grab component at Wylfa power station and the subsequent actions taken to prevent a recurrence were presented at Mold Crown court on 12 to 14 September 1995 and are now a matter of public record.