HC Deb 15 May 1995 vol 260 c84W
Mr. Home Robertson

To ask the Secretary of State for Scotland if he will make a statement on proposals by the Miller Amey consortium to depart from certain aspects of the confirmed plan for the A1 dual carriageway between Tranent and Haddington, and if he will require the contractor to design and construct this section of road in accordance with the confirmed plan. [21813]

Lord James Douglas-Hamilton

The contract awarded to Miller/Amey joint venture was on a "design and build" basis. This form of contract encourages the contractor to optimise the design, thus bringing benefits in which both the taxpayer and the industry can share. The amended proposals are subject to completion of their statutory procedures, including consultation, in the normal way. It is too early to say at this stage what the final outcome will be.

The Scottish Office has found that alternative proposals by contractors can often deliver improved value for money. This, of course, means that the funds voted by Parliament for trunk roads in Scotland will be able to purchase more new construction than would otherwise be possible using traditional tendering methods.

Back to