HC Deb 24 March 1995 vol 257 c396W
Dr. David Clark

To ask the Secretary of State for Defence what recent construction and repair work has been done to Long Marston army camp; and what was the cost. [16076]

Mr. Soames

Since 1 April last year, the construction of a tactical fuel handling facility has been completed and work has commenced on repairs to the water ring main system. Property management work, including repairs to boundary roads, concrete hardstandings and underground cabling has also been undertaken. The total cost of this work has been some £1.2 million.

Forward to