§ Mr. William RossTo ask the Secretary of State for Northern Ireland what sums have been expended to date on the bridge strengthening programme; and how long it will he and at what cost before the programme is complete. [32446]
§ Mr. MossIn the last three years, approximately £13.2 million has been expended on the bridge assessment and strengthening programme. Information prior to 1992–93 is not readily available and could be obtained only at disproportionate cost. The provision allocation for the 1995–96 financial year is £5 million.
It is planned that the assessment programme will be completed by 31 December 1998. The cost and the timing of the completion of the associated strengthening works will depend on the volume of work identified and the availability of finance.