To ask the Secretary of State for Transport what is the estimated cost of the A1 road development from Darrington to Hook Moor in West and North Yorkshire.

Mr. Watts

A total of £110 million.

Mr. O'Brien

To ask the Secretary of State for Transport what proposals he has to introduce the design, build, finance and operate concessions in respect of the proposed A1 new road developments; and if he will make a statement.

Mr. Watts

There are no proposals at present to introduce design, build, finance and operate projects in respect of proposed A1 new road developments, beyond the short length of A1 between Hook Moor and Bramham included as part of the M1-A1 link road design, build, finance and operate project and the A1 widening project between Alconbury and Peterborough in Cambridgeshire. Tenders for both were invited on 9 January.