HC Deb 28 April 1995 vol 258 cc728-9W
Mr. Morgan

To ask the Secretary of State for Wales, pursuant to his answer to the hon. Member for Swindon (Mr. Coombs) of 24 April,Official Report, column 369, what interim payments had already been paid (a) to Balfour Beatty with respect to the Cardiff bay barrage construction contract and (b) to contractors carrying out the sewer diversion contract connected with the barrage. [21680]

Mr. Redwood

Interim payments of £16.9 million have been paid to Balfour Beatty-Costain for barrage construction and £0.3 million has been paid for sewer diversion works.

Mr. Morgan

To ask the Secretary of State for Wales, pursuant to his answer to the hon. Member for Swindon (Mr. Coombs) on 24 April 1995,Official Report, column

£ million
To: 31 March 1994 1994–95 1995–96 1996–97 1997–98 Future Totals
Totals 22.3 22.3 44.4 48.1 36.6 17.3 191.0

Mr. Morgan

To ask the Secretary of State for Wales, pursuant to his answer to the hon. Member for Swindon (Mr. Coombs) of 24 April,Official Report, column 369, if he will list what categories of cost escalation apply to (a) the main contract with Balfour Beatty for the construction of the Cardiff bay barrage and (b) contracts for sewer diversion being funded by the Cardiff Bay development corporation; and if he will make a statement on how these categories have affected the difference between the October 1992 estimate and the present outturn forecast. [21681]

Mr. Redwood

This is an operational matter for the corporation and I will ask the chief executive of the corporation to respond.

Mr. Morgan

To ask the Secretary of State for Wales, pursuant to his answer to the hon. Member for Swindon (Mr. Coombs) of 24 April,Official Report, column 369, if he will specify how much of the £15.4 million for preliminary design work and the presentation of Bills to Parliament was (a) for preliminary design work and (b) for presentation of Bills to Parliament. [21683]

Mr. Redwood

Of the £15.4 million preliminary design and barrage Bill costs, £9.30 million was for preliminary design work and £6,066 million was for presentation of Bills to Parliament.

Mr. Morgan

To ask the Secretary of State for Wales, pursuant to his answer to the hon. Member for Swindon (Mr. Coombs) 24 April,Official Report, column 369, if he will specify what proportion of the construction of the barrage had been completed by 31 March. [21682]

Mr. Redwood

By 31 March 1995, the corporation estimate the construction of the barrage to be 8 per cent. complete. This does not represent the actual cost spent on barrage construction to date, which includes enabling works such as piling and dredging as well as construction materials already bought in.

Forward to