HC Deb 04 March 1994 vol 238 c81W
Mr. Denham

To ask the Secretary of State for Transport (1) on what date the contract with Bray's Detective Agency for surveillance of the Twyford down section of the M3 began; and on what date it will end;

(2) what is the total cost to date of the contract with Bray's Detective Agency for surveillance of the M3, Twyford down section.

Mr. Key

Bray's Detective Agency, Southampton, has been employed since March 1992 to service papers and collect evidence of trespass on the M3 construction site. At present, its contract runs until the end of July 1994. By the end of January this year, the agency had been paid approximately £228,000.

Mr. Denham

To ask the Secretary of State for Transport what is the total cost to date of legal action taken against protestors concerning the Twyford down section of the M3.

Mr. Key

The total cost of legal fees to date in connection with action against trespassers on the M3 construction site is approximately £165,000, excluding value added tax.

Mr. Denham

To ask the Secretary of State for Transport when it is expected the Twyford down section of the M3 will be completed.

Mr. Key

The motorway is due to be completed in the autumn.