§ Mr. SpearingTo ask the Secretary of State for Transport what has been the approximate cost of preparation and auxiliary work occasioned by works for the Jubilee line at Westminster station that are not part of the contracts for that line; and what is the principal expenditures and the source of funding from(a) public and (b) private bodies.
§ Mr. NorrisIn the parliamentary summer recesses of 1992 and 1993, London Underground Limited spent a total of around £3 million on utility diversions in the Westminster station area. All that expenditure was financed by the Government's grant to London Transport.