HC Deb 13 July 1994 vol 246 c609W
Mr. Mudie

To ask the Secretary of State for the Environment what is the estimated total cost of the refurbishment works on 1 to 19 Victoria street.

Mr. Eggar

I have been asked to reply.

1–19 Victoria street is being refurbished for reoccupation by DTI as its headquarters building. The work is expected to cost £61.4 million, net of VAT, £59 million of which is being provided by the landlord, Legal and General Property.