§ Mr. HuttonTo ask the Secretary of State for Defence what contracts were placed for refurbishment of the command centre under the south citadel building in Whitehall between 1979 and 1985; who were the main contractors; and what was the value of each contract.
§ Mr. AitkenFour main contracts were placed for the refurbishment of the command centre under the south citadel building in Whitehall between 1979 and 1985. The contractors were Griffiths McGee Demolition Co Ltd, Mirrless Blackstone Stamford Ltd, Taylor Woodrow Construction Ltd and Hayward Tyler Ltd. The total value of the four contracts when let was approximately £700,000.