HC Deb 20 December 1994 vol 251 cc999-1000W
Mr. Flynn

To ask the Secretary of State for Wales what financial penalties have been paid by the contractor on the Brynglas tunnels bypass scheme; and what new date has been agreed for its completion.

Mr. Gwilym Jones

The contract completion date for the M4 Brynglas tunnels and A4042 Malpas road relief scheme has been extended from 4 December 1994 to 5 February 1995. I am advised that the contractor will not achieve actual completion until summer 1995. Liquidated damages are not yet applicable.