HC Deb 05 December 1994 vol 251 c73W
Mr. Flynn

To ask the Secretary of State for Wales what was the original date for the completion of the Brynglas tunnels bypass; and what is now the expected date.

Mr. Gwilym Jones

The original contract completion date for the M4 Brynglas tunnels and A4042 Malpas road relief scheme was 20 March 1994. Extensions of time have been awarded giving a current contract completion date of 4 December 1994. Further extensions have been claimed by the contractor and the completion date is currently under review.