HL Deb 28 April 1994 vol 554 c49WA
Lord Bonham-Carter

asked Her Majesty's Government:

When the widening of the Ladbroke Grove Canal Bridge was started, when it was scheduled to be completed, and when it will be completed.

Lord Mackay of Ardbrecknish

Work began on this local authority bridge improvement scheme in January 1992, with a scheduled completion date of January 1994. Various difficulties have prolonged the works. Kensington and Chelsea, the lead local authority, now expect the works to be completed in autumn 1994.