HC Deb 26 October 1993 vol 230 c576W
Mr. Wallace

To ask the President of the Board of Trade what was the number of hours of operation and the electricity generated, in kilowatt hours, by the Orkney 3 MW wind turbine at Burgar hill in each year since 1988 and in 1993 to date.

Mr. Eggar

Operating records of the Orkney 3 MW wind turbine at Burgar hill are described in the table:

Year Hours run mKWh generated
1989 1,551 1.926
1990 1,103 1.549
1991 790 1.135
1992 3,662 5.152
1993

The machine has not operated in 1993 pending a decision on recommissioning it following completion of its experimental programme.

Mr. Wallace

To ask the President of the Board of Trade (1) what estimate he has made of the costs of repairing the crack in the rotor in the Orkney 3 MW wind turbine discovered in December 1992; and when he expects the repairs to be completed;

(2) if he will make a statement on the future operational programme for the Orkney 3 MW wind turbine.

Mr. Eggar

The turbine has completed its experimental programme and therefore its future depends on its viability as a generator of electricity. This is under consideration and my Department and Scottish Hydro-Electric plc hope to make a statement before the end of the year. The cost of repairing and recommissioning would be in the region of £50,000.