HC Deb 19 May 1993 vol 225 c156W
Mr. Simon Hughes

To ask the Secretary of State for Transport if he will make a statement on the status of the M3 extension through Twyford Down, and the planned timetable; if the extension is currently on schedule; and if contracts include penalty clauses for a time delay.

Mr. Kenneth Carlisle

The main works for the construction of the Bar End to Compton section of the M3 have been in progress since October 1992 and are due for completion in autumn 1994. A three-week extension of time has been granted to the contractor in respect of difficulties with the appointment of a steel work subcontractor for the Shawford railway bridge. The contract includes the normal provision for liquidated damages if the works are completed later than the contract completion date.