HC Deb 10 December 1993 vol 234 cc375-6W
Mr. Mallon

To ask the Secretary of State for Northern Ireland (1) if he will give the date of receipt of an application for welfare adaptations at 17 O'Reilly park, Killeen, Newry, and the dates when the application was referred to the occupational therapist; when an occupational therapist report was received; when an architect was appointed; and when work is due to be completed;

(2) if he will give details of the reasons for delays in processing the application for welfare adaptations for 17 O'Reilly park, Killeen, Newry.

Mr. Atkins

This is a matter for the Northern Ireland Housing Executive but I understand from the chief executive that a verbal application was received in early January 1993 and referred to the occupational therapist on 7 January 1993 whose report was received on 29 January 1993.

A Housing Executive architect was appointed to carry out a feasibility study on 2 February 1993 and this was completed in May 1993. The scheme was passed to a consultant architect in June 1993 for detailed plans to be drawn up. These plans required amendments to incorporate comprehensive improvements to the dwelling which were brought forward to minimise disruption to the tenants.

The detailed plans were completed on 22 November 1993 and were approved by the Housing Executive on 2 December 1993. The work is due to start in January 1994 and be completed by April 1994. The work should commence within the target timescale recently set by the Executive for carrying out major adaptations which involve an extension to a disabled person's home.