HC Deb 23 November 1992 vol 214 cc510-4W
Mr. Blunkett

To ask the Secretary of State for Health what capital projects costing £1 million or more are currently scheduled by each regional health authority; what is the anticipated date of completion for each project; what was the original projected completion date for each project; and how many projects and at what total value, have been removed from the 1992–93 capital programme in each regional health authority.

Mr. Sackville

[holding answer 20 November 1992]: The latest information available on capital schemes costing over £ 1 million under construction in each regional health authority area is shown in the table. Management of the capital programme is a matter for individual regional health authorities, and information on schemes in planning or removed from the programme is not held centrally. In total, some 400 schemes each costing more than £1 million are at various stages of planning, design and construction throughout the NHS in England.

Schemes £1 million and over which are under construction
Authority and Scheme Contract target completion date Latest estimated completion date
Northern RHA
Furness General Scheme 3 Phase 1 (Mental Illness) 16 January 1993 3 February 1993
Royal Victoria Infirmary Ante-Natal Clinic 25 September 1993 25 September 1993
RVI-Unification of Obstetrics and Gynaecology 31 March 1993 31 March 1993
Sunderland General Scheme 2 Phase 2 (ward block) 28 July 1993 4 August 1993
W. Cumberland GH rationalisation maternity/geriatric 15 May 1994 15 May 1994
Wansbeck General Hospital Scheme 1 Phase 1 (Nucleus) 29 May 1992 11 December 1992
Yorkshire RHA
Chapel Allerton (Newton Green Wing additions) 24 December 1993 24 December 1993
Harrogate DGH Acute Geriatric Improvements Scunthorpe DGH Phase 4A(3) Path. 2 and Hydro 16 January 1995 13 February 1994 16 January 1995 13 February 1994
St. James Redevelopment Phase 4 (Nucleus) 9 May 1994 9 May 1994
St. Lukes Development Phase 1A (Nucleus) 25 February 1993 25 February 1993
Trent RHA
Bassetlaw DGH Phase 2A 12 March 1993 12 March 1993
Clay Cross Community Hospital 28 February 1994 28 February 1994
Derby City Hospital Mental Illness Unit 16 January 1994 28 June 1993
Glenfield DGH Phase 3 Cardiothoric Dept. 27 August 1993 27 August 1993
Kings Mill DGH OPD & GU Clinic 4 October 1992 30 October 1992
Leicester Health Authority Cook/Chill 0 May 1992 30 October 1992
Lincoln County Phase 2 2 October 1992 30 November 1992
Mansfield Community 2 new wards 26 March 1993 26 March 1993
Notts City Renal/ Radiotherapy 30 November 1992 8 May 1993
Rotherham DGH Phase 3B Geriatric Unit 24 June 1994 24 June 1994
East Anglia RHA
Ipswich HRW—pathology extension PHI 30 November 1992 1 December 1992
Risbridge facilities for mentally handicapped 4 March 1993 4 March 1993
UEA School of Physio+ O/T 6 November 1993 6 November 1993
Waveney Hospital—ESMI Unit 18 December 1992 18 December 1992
North West Thames RHA
Central Middlesex Acute
Secure Unit/Mother and Baby Unit 28 May 1993 28 May 1993
Charing Cross Hospital
Linear Accident and new building 26 October 1992 26 October 1992
Vincent Square Health Care Centre (W and C) 17 February 1993 17 February 1993
Westminster and Chelsea Hospital 9 June 1992 30 November 1992
North East Thames RHA
Chase Farm Regional Secure Unit 12 October 1992 2 November 1992
Authority and Scheme Contract target completion date Latest estimated completion date
Daleham Gardens
Intensive Rehabilitation Unit/Health Clinic 7 February 1993 7 February 1993
Goodmayes DGH 10 November 1992 10 November 1992
South East Thames RHA
Guys Phase 3 Stage Superstructure 16 May 1993 19 December 1993
Kings College Hospital— Theatres 27 August 1993 17 September 1993
Knights Hill—ESMI Unit 2 November 1992 9 November 1992
Mid Kent Radiotherapy 3 October 1992 21 December 1992
RSCH Tower Block Internal/External Refurbishment 18 March 1993 18 March 1993
St. Martin's Hospital Phase 1—MH1 21 May 1993 21 May 1993
St. Martin's Hospital Phase 2
Office Kitchen Block 22 January 1993 22 January 1993
St. Thomas' Hospital—A and E Upgrade/ Extension 24 January 1994 24 January 1994
Thanet Mental Health Development 7 May 1993 7 May 1993
Uckfield Community Hospital 29 October 1993 29 October 1993
William Harvey Hospital
1A Rehabilitation and NI Unit 20 January 1993 6 September 1993
South West Thames RHA
Barnes ESMI Phase 2 (Nucleus) 5 January 1993 5 January 1993
Frimley Park Hospital Phases 1 and 2 12 February 1993 12 February 1993
St. John's Twickenham Redevelopment Phase 1 7 February 1993 7 February 1993
Tolworth Hospital—New Ward Unit 6 June 1993 6 June 1993
Woking Hospital Development—Phase 1
Rehab Centre 11 December 1993 11 December 1993
Wessex RHA
Alton Community Hospital/LMT
Redevelopment Phase 1 4 January 1991 30 November 1992
Gosport Community Hospital Phase 1A 30 April 1993 30 November 1992
Queen Alexandra Ophthalmology Department 16 July 1993 16 July 1993
Royal United Hospital— Bath and Wessex Replacement 23 June 1993 23 June 1993
Southampton General East Wing Window Replacement 18 February 1993 18 February 1993
St. Andrew's Hospital— Chippenham Catering 00 August 1993 00 August 1993
St. Mary's Portsmouth Phase 2A and 2B 26 June 1994 26 June 1994
Oxford RHA
Amersham—Dermatology Unit 8 November 1993 8 November 1993
Ashurst—Phase 1 10 August 1993 10 August 1993
Central Area—CPU 13 October 1992 13 November 1992
Southern Area—CPU 1 March 1993 1 March 1993
Wexham Park—Post Graduate Medical Centre 2 August 1993 2 August 1993
South Western RHA
Bridgewater EPD 18 beds
18 day places 1 April 1993 1 April 1993
Authority and Scheme Contract target completion date 27 April 1994 Latest estimated completion date
Cheltenham Acute Mental Illness 27 April 1994
Derriford DGH Phase 2 14 December 1992 3 February 1993
Derriford DGH Phase 3A Maternity Unit 29 October 1993 29 October 1993
Derriford Fire Precautions Work 00 December 1992 00 December 1992
Frenchay DGH Phase 1A 4 December 1992 4 December 1992
Gloucester Royal Pathology 23 October 1992 14 December 1992
Gloucester Royal Waste Disposal Complex 00 May 1992 00 August 1992
Lyngford House Taunton Phase 11 21 January 1993 21 January 1993
Manor Park Hospital New Mental Illness Unit 19 September 1992 19 September 1992
Watford Gardens Newcourt Hospital Replacement 11 December 1992 11 December 1992
Royal Devon and Exeter (Wonford) Priority 2 (Nucleus) 21 July 1995 21 July 1995
Royal Devon and Exeter (Wonford) Support Services 11 March 1994 11 March 1994
Southmead Hospital— Orthopaedic Unit (Nucleus) 29 November 1992 29 November 1992
Southmead Hospital Mental Illness Unit 4 October 1992 16 November 1992
Taunton and Somerset Hospital Phase 2 26 March 1995 31 August 1994
Torbay DGH Surgical Services (Part only) 31 May 1993 31 May 1993
Totnes Community Hospital 20 June 1993 20 June 1993
West Cornwall Penzance New Ward Block 9 September 1993 9 September 1993
West Midlands RHA
Burton DGH Phase 2.4 main hospital 15 February 1993 15 February 1993
Conversion of surgical square to medical beds 18 December 1992 18 December 1992
Dudley DGH Mental Health Development 31 July 1993 31 July 1993
East Birmingham— Maternity/ENT Theatres/Pathology 4 September 1992 1 October 1992
George Eliot Nuneaton Phase 3 (Nucleus) 9 July 1993 18 July 1993
Hollymoor Hospital Community Unit 28 September 1992 11 January 1993
Kidderminster DGH Phase 6 (Nucleus) 24 July 1995 24 July 1995
Rowley Regis Community Hospital Sandwell 10 December 1993 27 January 1994
Solihull DGH Phase 2 Contract 1 (Nucleus) 10 April 1994 10 April 1994
Authority and Scheme Contract target completion date Latest estimated completion date
St. Cross Rugby Phase 3
(Nucleus) 14 September 1992 3 November 1992
Warwick DGH Phase 2 3 October 1993 3 October 1993
Mersey RHA
Clatterbridge Hospital Redevelopment Phase 2 6 December 1993 6 December 1993
Fazakerley Hospital A&E Department 16 April 1993 16 May 1993
Hospital for Obstetrics and Gynaecology 20 Janaury 1995 20 January 1995
Warrington DGH Phase C Whiston Phase I Regional Burns and Plastic Unit 30 September 1993 8 October 1993 13 September 1993 8 October 1993
North Western RHA
Birch Hill Hospital-
Mental Illness Unit 24 January 1993 24 January 1993
Calderstones Hospital— Replacement Kitchen 5 February 1993 5 February 1993
Chorley DGH Phase 3A 12 March 1995 12 March 1995
Manchester Royal Infirmary—Mental Illness Unit 22 June 1993 22 June 1993
Manchester Royal Infirmary—Pathology
and Mortuary 1 January 1995 1 January 1995
Manchester Royal Infirmary— Phase 2 Ass. Works
PHB 28 September 1993 29 September 1993
Manchester Royal
Infirmary—School of Physiotherapy 12 January 1993 12 January 1993
North Manchester General—Cook Chill
Catering Development North Manchester General— 7 September 1992 23 October 1992
F and G Block (Main Phase) March 1994 March 1994
North Manchester General—Phase 1 23 May 1993 23 May 1993
Ormskirk District General Hospital Phase 1 9 March 1993 9 March 1993
Post Graduate Medical Centre 2 July 1993 2 July 1993
Prestwich Mental Health Centre for Deaf People 1 February 1993 30 January 1993
Queens Park—PH3 Maternity and Gynaecology 25 July 1994 25 July 1994
Royal Lancaster Infirmary —Phase 3 18 August 1995 18 August 1995
Wythenshawe Integrated Thoracic Medicine 9 November 1992 23 November 1992