§ Rev. Martin SmythTo ask the Secretary of State for Northern Ireland what is the average length of time taken to grant planning permission for conversion of property and commercial development.
§ Mr. AtkinsFor the year ended 31 March 1992 the median number of calendar days taken to decide planning applications for the conversion of a property to another use was 67. The corresponding figure for applications involving commercial development was 70.
§ Rev. Martin SmythTo ask the Secretary of State for Northern Ireland how many requests for planning permission take over two years from formal application to decision.
§ Mr. AtkinsOf the 18,341 planning applications determined in the year ended 31 March 1992, 62 or 0.3 per cent. took over two years to decide.