§ Mr. William PowellTo ask the Secretary of State for Transport what improvements to the A13 between the North Circular road and Butcher row are currently being undertaken; at what cost; and when they will begin and be completed.
§ Mr. NorrisThe present estimated cost of works (including any advance works) and construction dates are as follows:
Scheme Estimated works cost(£ million) Planned start Planned finish Butcher row junction 1 1993 1994 West India Dock road junction Interim 4 (Completed April 1992) Final 1 1993 1993 Cotton street-Blackwall tunnel junction(A 102) 7 1993 1994 Ironbridge to Canning Town improvements 53 1994 1997 Prince Regent lane(Al 12) junction 36 1994 1996 East Ham Manor way(A117) junction 33 1994 1996 All schemes are subject to the availability of funds and the satisfactory completion of statutory procedures.