HC Deb 29 June 1992 vol 210 c393W
Mr. Tom Clarke

To ask the Secretary of State for Transport if he will make a statement on the level of investment in new locomotives he has authorised for British Rail.

Mr. Freeman

The level and timing of British Rail's investment in new locomotives are determined by operational requirements and available resources. New locomotives are not always required to replace those withdrawn: the regional railways sector has replaced virtually all its loco-hauled services with the faster and more efficient class 158 diesel multiple units.

Locomotive builds authorised and yet to be fully completed are 34 high-speed train sets and 37 class 92 locomotives for channel tunnel services; and 100 class 60 locomotives for domestic freight services, at a total cost of over £700 million at current prices.