HC Deb 08 July 1992 vol 211 c187W
Mr. Morgan

To ask the Secretary of State for Wales what progress has been made in setting up a trust fund for the transfer of assets from the Cardiff Bay development corporation for the purpose of accumulation of capital assets.

Mr. David Hunt

Cardiff Bay development corporation has considered a number of options for meeting the costs of operating the barrage and the inland bay after its dissolution. A trust fund was one of the options considered by the corporation but the Government have not yet taken a final decision on the preferred choice.

Mr. Morgan

To ask the Secretary of State for Wales what is his most up-to-date estimate of the cost of the mitigation works for the provision of alternative feeding grounds for wading birds on the south Wales foreshore on an out-turn cost on the comparable timing of construction basis to the £167.4 million cost of the barrage in his answer of 26 June,Official Report, column 340.

Mr. David Hunt

The out-turn cost of the mitigation works will depend on the method and phasing of construction, which will not be known before the feasibility study is completed in the autumn.

Back to
Forward to