HC Deb 10 February 1992 vol 203 c365W
18. Mr. Paice

To ask the Secretary of State for Transport when he expects the dualling of the A11 between Newmarket and Four Wentways to be completed.

Mr. Chope

Tenders for the work were received on 4 February. Assessment, award of contract and mobilisation of the successful contractor normally take about two months. The period for completion in the tender documents is two years, which means the road would be dualled by spring 1993.