Actual start of works Programmed start of works Programmed/actual completion Contract 1: Catthorpe Interchange February1990 — Summer 1990 Contract 2: Catthorpe to Rothwell — late 1991 late 1993 Contract 3: Catthorpe to Rothwell — late 1991 late 1993 Contract 4: Rothwell to Kettering March 1990 — May 1991 Contract 5 (N): Kettering Northern Bypass — January 1992 March 1993 Contract 5 (S): Kettering Southern Bypass February 1990 — November 1991 Contract 6: Kettering to Thrapston May 1989 — November 1990 Contract 7: Thrapston to Brampton November 1989 — 1 December 1990 west,6 February 1991 east Contract 8: Thrapston to Brampton 5 August 1991 — Spring 1993