HC Deb 22 October 1991 vol 196 cc474-5W
Sir John Farr

To ask the Secretary of State for Transport what is his latest date for completion of the Al-M1 link road; and if he will advance his plans in this respect.

Mr. Chope

All remaining contracts are programmed to be let by the end of this year. The road should be completed by the end of 1993. Although this is subject to the effects of the action of the Society for the Preservation of the Field of the Battle of Naseby in fragmenting one plot within contract 2 into multiple ownership.

The position for each contract is as follows.

Actual start of works Programmed start of works Programmed/actual completion
Contract 9: Thrapston to Brampton November 1991 Summer 1993
Contract 10: Advance works for Railway Bridge on Kettering
Northern Bypass April 1990 November 1991