HC Deb 21 March 1991 vol 188 c210W
Mr. Roy Hughes

To ask the Secretary of State for Transport when he expects the current repairs and maintenance work on the Severn bridge to be completed; and when the bridge will become fully operational.

Mr. Chope

The resurfacing contract is due for completion in the late summer, when the bridge will be fully operational in its final configuration.

Mr. Roy Hughes

To ask the Secretary of State for Transport what was the original estimated cost of the current repairs and maintenance work on the Severn bridge; and what is the latest estimated cost.

Mr. Chope

The current estimated cost of the repair and strengthening work is £80 million. The estimates have been revised many times over the years as changes to the scope of work have become necessary and an original estimated cost on a comparable basis with the current estimate is not available.