HC Deb 14 March 1991 vol 187 c630W
Mr. Morgan

To ask the Secretary of State for Energy what consultations he has had with the nuclear installations inspectorate concerning the Westinghouse digital protection system governing the computerised safety monitoring system for the Sizewell B nuclear power station.

Mr. Heathcoat-Amory

The Health and Safety Executive's nuclear installations inspectorate—NII—is assessing the computerised protection systems for Sizewell B as part of the continuing licensing process. It is also assessing the secondary protection system, which is fitted to Sizewell B in addition to the digital system, and which employs established United Kingdom technology. The nuclear installations inspectorate will not permit fuel to be loaded into the reactor until it has assessed Nuclear Electric's safety case for the station and found it to be adequate.