HC Deb 04 March 1991 vol 187 c43W
Mr. Clifford Forsythe

To ask the Secretary of State for Northern Ireland when the enabling legislation authorising Northern Ireland Railways to install automatic half barriers to selected open crossings is to be tabled; and if he will name the crossings concerned.

Mr. Needham

Orders in relation to the conversion of 13 automatic open crossings to automatic half-barrier level crossings are in preparation and are scheduled to come into operation as follows:

Crossing Operation date
Slaght 2 September 1991
Killagan 16 September 1991
Galgorm 30 September 1991
Broughdone 14 October 1991
Glarryford 28 October 1991
Dunloy 11 November 1991
Caldanagh 25 November 1991
Ballyboyland 9 December 1991
Barmouth 6 January 1992
Umbra 20 January 1992
Magilligan 3 February 1992
Bellarena 17 February 1992
Cromore 2 March 1992