HC Deb 20 December 1991 vol 201 cc357-8W
Mr. Barry Jones

To ask the Secretary of State for Wales what is the cost, expected start and completion date of the Deeside Park to Drove Corner road scheme.

Sir Wyn Roberts

The scheme is expected to start between April 1994 and March 1997 at a cost of around £17 million. Construction is likely to take two years.

Mr. Barry Jones

To ask the Secretary of State for Wales what is the cost and expected start and completion date of the Woodbank Junction to Deeside Park road scheme.

Sir Wyn Roberts

This scheme is planned to start between April 1994 and March 1997 at a cost of around £16 million. Construction is likely to take about one and a half years.