§ Mr. DobsonTo ask the Secretary of State for Energy (1) when he will publish the updated cost estimates for Sizewell B which Nuclear Electric sent him on 16 May;
(2) whether the estimates for the updated cost of Sizewell B which he has received from Nuclear Electric include provision for the costs associated with the intended follow-on pressurised water reactors.
§ Mr. Matthew TaylorTo ask the Secretary of State for Energy (1) whether any new information has been received from Nuclear Electric regarding the costs of a single development of a pressurised water reactor; and if he will make a statement;
(2) if he will publish the most recent cost estimates for Sizewell B from Nuclear Electric; and if he will make a statement.
§ Mr. WakehamNuclear Electric plc has just sent to me its latest progress report on Sizewell B and will discuss it with my Department. The projected costs of the station are a matter for NE. It will decide what to publish when the discussions with my Department are complete.
§ Mr. Frank CookTo ask the Secretary of State for Energy when he or another Minister in his Department last visited the Sizewell B nuclear power plant site; and if he will make a statement.
§ Mr. BaldryI visited Sizewell on 10 April.